LNG Regasification: Converting Liquid Back to Gas

Regasification is the process of warming LNG from -162°C back to gaseous state for pipeline delivery. Global regasification capacity in 2026 stands at ~1,100 MTPA, significantly exceeding liquefaction capacity (~520 MTPA), creating a buyer's market. Regasification terminals use specialized vaporizers that extract heat from seawater, ambient air, or combustion to safely warm LNG at rates up to 1,000 MMcf/d per terminal.

The Regasification Process

Regasification reverses liquefaction through controlled heat addition:

Process Steps

  1. Unloading: LNG transferred from carrier to storage tanks (6-12 hours for 174,000 m³ vessel)
  2. Storage: LNG held in insulated tanks at -162°C, atmospheric pressure
  3. Sendout: LNG pumped from storage through vaporizers
  4. Vaporization: Heat applied to convert LNG to gas (primary focus of this article)
  5. Odorization: Mercaptan odorant added (natural gas is odorless; smell aids leak detection)
  6. Metering & Pressure Control: Gas measured and pressurized (50-100 bar) for pipeline injection

Energy Requirements

Heat Needed per Tonne LNG:

  • Sensible Heat: Warming from -162°C to 15°C: ~220 kJ/kg
  • Latent Heat: Phase change (liquid → gas): ~510 kJ/kg
  • Total: ~730 kJ/kg (0.2 kWh/kg)

This is far less than the 250-300 kWh/tonne required for liquefaction (cooling consumes ~100x more energy than warming).

Vaporizer Technologies

Vaporizer Technology Comparison
Type Heat Source Efficiency CAPEX Market Share
ORV (Open Rack Vaporizer) Seawater 99%+ (free heat) Low ~55%
SCV (Submerged Combustion) Natural gas combustion ~85% (fuel cost) Medium ~20%
AAV (Ambient Air Vaporizer) Atmospheric air 99%+ (free heat) Very Low ~15%
IFV (Intermediate Fluid) Propane/glycol loop ~90% High ~5%
HOIV (Heat Exchanger) Industrial waste heat 99%+ (free heat) Medium ~5%

1. Open Rack Vaporizer (ORV) - Industry Standard

Operating Principle:

  • LNG flows through aluminum tubes arranged in vertical panels ("racks")
  • Seawater cascades over tubes from top, transferring heat
  • LNG vaporizes as it rises through tubes; exits as gas at ~5-10°C
  • Discharge seawater is ~4-6°C colder than intake

Design Specifications:

  • Tube Material: Aluminum alloy (5083 or 5052) - excellent low-temp properties
  • Typical Size: 12m high × 4m wide panel; 10-20 panels per vaporizer
  • Capacity: 150-250 tonnes/hour per vaporizer unit
  • Seawater Flow: ~4,000 m³/h per 200 tonne/h unit

Advantages:

  • Zero fuel cost (uses ambient seawater heat)
  • High reliability (no moving parts in heat exchanger)
  • Low operating cost (~$0.10-0.15/MMBtu)
  • Proven technology (used since 1970s)

Disadvantages:

  • Location-dependent: Requires coastal site with deep water access
  • Environmental concerns: Discharge water 4-6°C colder affects marine life (requires mitigation)
  • Cold climate issues: Seawater can freeze in extreme cold; requires SCV backup
  • Corrosion: Seawater is corrosive; requires cathodic protection and regular maintenance

Seawater Intake Requirements:

Example: 1,000 MMcf/d (7 MTPA) Terminal

  • LNG throughput: ~300 tonnes/hour
  • Heat required: ~220 MW thermal
  • Seawater flow: ~20,000 m³/h (5.5 m³/s)
  • Temperature drop: 5-6°C

2. Submerged Combustion Vaporizer (SCV)

Operating Principle:

  • Natural gas burned underwater in combustion chamber
  • Hot combustion gases (1,800°C) bubble through water bath
  • Water heated to 30-60°C
  • LNG flows through submerged tubes, absorbing heat from hot water

Design Specifications:

  • Fuel Consumption: ~1.5-2.0% of throughput gas
  • Capacity: 100-300 tonnes/hour per unit
  • Efficiency: 85-90% (some heat lost to atmosphere)
  • Water Bath: 500-1,000 m³ per unit

Advantages:

  • Location-flexible: Can be built inland (no seawater needed)
  • Works in any climate (no freezing risk)
  • Compact footprint vs. ORV
  • Fast startup (15-30 minutes vs. hours for ORV)

Disadvantages:

  • Fuel cost: ~$0.30-0.50/MMBtu operating expense
  • CO₂ emissions: ~0.5 kg CO₂/MMBtu (climate concern)
  • Water vapor plume: Visible steam discharge (aesthetic/regulatory issue)

Typical Use Cases:

  • Peak Shaving: Backup to ORV during winter demand spikes
  • Inland Terminals: Where seawater unavailable
  • FSRU: Floating terminals use SCV for flexibility

3. Ambient Air Vaporizer (AAV)

Operating Principle:

  • LNG flows through finned aluminum tubes
  • Natural air convection (or fans) transfers ambient heat to tubes
  • No external energy input required (passive system)

Design Specifications:

  • Tube Array: Vertical or horizontal configuration with extensive fin area
  • Capacity: 10-50 tonnes/hour per unit (smaller than ORV/SCV)
  • Footprint: Large - requires 10-20x more space than ORV for same capacity

Advantages:

  • Zero operating cost (no fuel, no pumps in passive design)
  • Extremely simple and reliable
  • No environmental discharge (no seawater, no emissions)
  • Ideal for small-scale LNG (trucking terminals, peak shaving)

Disadvantages:

  • Large land requirement (prohibitive for large terminals)
  • Climate-dependent: Capacity drops significantly in cold weather
  • Icing: Frost/ice buildup on fins reduces efficiency; periodic defrosting needed
  • Scaling limitation: Not practical above ~100 MMcf/d due to footprint

Best Applications:

  • Small-scale LNG terminals (trucking, satellite stations)
  • Peak shaving facilities (seasonal use)
  • Remote locations where simplicity valued over efficiency

4. Intermediate Fluid Vaporizer (IFV)

Operating Principle:

  • Closed-loop system using propane or glycol as heat transfer fluid
  • Intermediate fluid heated by seawater, combustion, or waste heat
  • LNG vaporized in separate heat exchanger (no direct contact)

Advantages:

  • Prevents LNG contact with seawater (safety/environmental benefit)
  • Can use multiple heat sources simultaneously
  • Better temperature control than ORV

Disadvantages:

  • High CAPEX: Requires additional equipment (pumps, heat exchangers)
  • Maintenance: More complex than ORV
  • Efficiency loss: Two-stage heat transfer reduces overall efficiency

Import Terminal Operations

Typical Terminal Layout

A modern 7 MTPA (~1,000 MMcf/d) import terminal includes:

  • Ship Unloading Berth: Jetty with 4-6 unloading arms (1,200-1,500 m³/h per arm)
  • Storage Tanks: 2-4 tanks, each 180,000-200,000 m³ capacity
  • Sendout Pumps: High-pressure cryogenic pumps (150-300 bar discharge)
  • Vaporizers: 4-8 ORV units + 2-3 SCV (backup/peak)
  • Metering & Odorization: Gas quality adjustment and measurement
  • Pipeline Connection: High-pressure (50-100 bar) tie-in to transmission grid

Unloading Process

Phase Duration Description
Berthing & Connection 2-3 hours Ship moors; loading arms connected; safety checks
Cooldown 1-2 hours Pipelines pre-cooled with LNG vapor to prevent thermal shock
Cargo Transfer 10-14 hours LNG pumped at 8,000-12,000 m³/h (174,000 m³ cargo)
Disconnection 1-2 hours Arms drained, disconnected; ship prepares to depart
Total Port Time 14-20 hours Varies by cargo size and terminal efficiency

BOG Handling at Import Terminals

Boil-off gas generated during unloading and storage must be managed:

  • BOG Compressor: Compress BOG to 50-80 bar, inject into sendout pipeline
  • Reliquefaction: Some terminals have small reliquefaction units to return BOG to storage
  • Flare (Emergency): Burn excess BOG if system capacity exceeded (avoided due to emissions)

Sendout Flexibility

Modern terminals can modulate sendout from 10% to 110% of design capacity:

  • Base Load: Continuous sendout at ~70-80% capacity
  • Peak Mode: 100-110% during winter demand or pipeline maintenance
  • Minimum Sendout: 10-15% to maintain system operability

Cold Energy Recovery

LNG at -162°C contains significant cold energy (~830 kJ/kg) that is typically wasted during regasification. Some terminals capture this for value-added applications:

Cold Energy Applications

Application Energy Use Value Adoption
Power Generation Cryogenic turbine (Rankine cycle) 5-7 kWh/tonne LNG ~15% of terminals
Air Separation Liquefy air to separate N₂/O₂ High (co-located with industrial users) ~5%
Cold Storage Refrigerate warehouses Medium (logistics hubs) ~5%
Desalination Freeze desalination process Medium (water-scarce regions) <5%
CO₂ Capture Liquefy CO₂ for sequestration High (with CCS infrastructure) Pilot stage

Power Generation Example

Direct Expansion Turbine:

  • LNG pumped to high pressure (80-100 bar)
  • Expanded through turbine while vaporizing (like steam turbine)
  • Generates ~5-7 kWh per tonne LNG
  • Economic Value: $0.30-0.50/MMBtu at $0.10/kWh electricity price

Challenge: High CAPEX ($50-100M for 7 MTPA terminal); payback 10-15 years.

Why Cold Recovery Isn't Universal

  • Low value: 5-7 kWh/tonne only worth ~$0.50-0.70/tonne
  • High CAPEX: Equipment costs $50-150M for large terminal
  • Complexity: Adds operational risk and maintenance burden
  • Location: Requires nearby customer for cold energy or grid connection for power

Safety Systems

LNG Rollover Prevention

Rollover is rapid vaporization caused by density stratification in storage tanks:

  • Cause: Different LNG compositions (e.g., Qatar heavy LNG layered over Australian light LNG)
  • Risk: Sudden BOG surge can overpressure tank
  • Prevention: Blend incompatible cargoes slowly; use multiple fill points; recirculation pumps

Emergency Shutdown (ESD) Systems

Triple-redundant safety systems at import terminals:

  • Level 1: Automated process shutdown (leak detection, overpressure)
  • Level 2: Tank isolation (emergency valves close in <30 seconds)
  • Level 3: Ship quick-release couplings (vessel can disconnect in emergency)

Fire Protection

  • Water Curtains: High-pressure spray to disperse LNG vapor clouds
  • Dry Chemical: Powder suppression for confined fires
  • Foam Systems: Cover LNG pools to prevent vaporization

Regasification Economics (2026)

Terminal Construction Costs

Component Cost (7 MTPA Terminal) % of Total
Storage Tanks (3×180,000 m³) $300-400M 40-50%
Vaporizers & Sendout Equipment $150-200M 20-25%
Jetty & Unloading Arms $100-150M 15-20%
Utilities, Piping, Instrumentation $100-150M 15-20%
Total CAPEX $650-900M 100%

Operating Costs

  • Vaporization (ORV): $0.10-0.15/MMBtu
  • Vaporization (SCV): $0.30-0.50/MMBtu (fuel cost)
  • Labor & Maintenance: $0.05-0.10/MMBtu
  • Total Regas Fee: $0.30-0.60/MMBtu (typical terminal tariff)

Comparison: Land-Based vs. FSRU

Parameter Land-Based Terminal FSRU
CAPEX $650-900M (7 MTPA) $200-350M (5 MTPA)
Development Time 4-6 years 12-18 months
Operating Cost $0.30-0.50/MMBtu $0.50-0.80/MMBtu (lease + opex)
Flexibility Permanent Relocatable
Capacity Up to 30+ MTPA 3-6 MTPA typical

Key Takeaways

  • Regasification requires ~730 kJ/kg heat input, ~100x less energy than liquefaction
  • Open Rack Vaporizers (ORV) dominate (55% share) due to zero fuel cost
  • Typical terminal: $650-900M CAPEX for 7 MTPA capacity
  • Regasification fee: $0.30-0.60/MMBtu (ORV-based terminal)
  • Global regasification capacity: ~1,100 MTPA vs. 520 MTPA liquefaction (2026)
  • Cold energy recovery adds $0.30-0.50/MMBtu value but high CAPEX
  • FSRUs offer 3x faster deployment than land terminals (12-18 months vs. 4-6 years)
  • Ship unloading: 14-20 hours for 174,000 m³ cargo